Replacement of Natural Gas System Phase II
Maxwell AFB Montgomery, Alabama
Contract # FA3300-14-C-0027 $1,149,308.88
Stephens Furnished all plant, labor, equipment, and materials and performed all operation in connection with Replacement of Natural Gas System. The gas distribution system replacement included the installation of the gas main, all specified fittings, valves, directional drilling, erosion control, grassing, rock or muck excavation and other required incidental items of work. The work included shall include from the connecting to the existing system to a connection at each existing gas meter/regulator. Most of the work was done by directional drilling with some connection being done by digging a trench to connect to existing meters/regulators.